The Mu2e experiment has prepared a Technical Design Report (TDR) describing a world-class facility that searches for the Charged-Lepton-Flavor-Violating process of a muon converting to an electron in the field of a nucleus and provides discovery sensitivity to a broad array of new physics models. The project is seeking CD-2/3b approval from the DOE.

For assistance in obtaining any documentation, references, etc., please contact . For document content questions, please contact the appropriate L2 manager (see Project Contact List).

Overview Documents

Title Mu2e-doc-# Title Mu2e-doc-#
Technical Design Report 4299 Mu2e Project/Collaboration Org Chart PDF file
Resource and Gantt Chart 4315 Critical Path 4315
Indirect Rates Rules 765 Contingency Rules 459
Milestones 4301 Risk Register 4320
Cost Book 4308 Design Review Plan 5061

Documents from Past Reviews

Title Mu2e-doc-# Title Mu2e-doc-#
Final Report from DOE CD2/3b Review (October 2014) 5035 Responses to recommendations from DOE CD2/3b Review 5040
Final Report from DOE Independent Cost Estimate/Review (August 2014) 4680 Final Report - Surveillance Review Report of the FRA EVMS (Dec 2014) 5053  
Final report from CD-2/3b Director's Review (July 2014) 4404 Responses to recommendations from CD-2/3b Director's Review 4405
Final report from DOE CD-3a Review (June 2014) 4317 Responses to recommendations from DOE CD-3a Review (June 2014) 4316
Feedback from DOE Briefing (February 2014) 4154 Responses to feedback from DOE Briefing (February 2014) 4155
Feedback from DOE Briefing (September 2013) 3456 Responses to feedback from DOE Briefing (September 2013) 3457
Final report from DOE Mini Review (April 2013) 2938 Responses to recommendations from DOE Mini Review (April 2013) 2939
Final report from DOE Mini Review (November 2012) 2577 Responses to recommendations from DOE Mini Review (November 2012) 2579
Final report from DOE CD-1 Review (June 2012) 2357 Responses to recommendations from DOE CD-1 Review 2358
Final report from CD-1 Director's Review (April 2012) 2209 Responses to recommendations from CD-1 Director's Review 2240
Final report from Independent Design Review (May 2011) 1563 Responses to recommendations from 2011 Independent Design Review 2067
Closeout report from CD-0 review 382 CD-0 Mission Need Statement 720