DOE Independent Project Review of Mu2e
Dec 10-12, 2019

Tracker

The Mu2e tracker provides the primary momentum measurement for conversion electrons. The tracker must identify and measure 105 MeV/c electrons while rejecting backgrounds, and it must provide this functionality while situated in the warm, evacuated bore of a superconducting solenoid that provides a uniform magnetic field of 1 Tesla.

Tracker Design, Schedule and Planning Documents

Title Mu2e-doc-# Title Mu2e-doc-#
Technical Design Report
4299        
Milestone Dictionary 4301 WBS Dictionary 4300
Monthly EVMS Performance Report - July 28056 Monthly EVMS Performance Report - August 28495
Monthly EVMS Performance Report - September 29100 Monthly EVMS Performance Report - October 29919
Monthly Performance Graphics 4659   
Gantt Chart 29919 Critical Path 30307
Baseline Schedule 30307 Forecast 29919
Monthly RLS Turn-around Status Collection Sheet 2999 Dollarized RAM 4312
Tracker Work Authorization Documents List Tracker Variance Reports List
Corrective Actions Log 4930 Change Control Procedure 2971
Change Request Log 4600 Change Control Topic List
Change Control by CAM & CA Instructions Mu2e Risk Register 4320
Tracker Institutional Responsibilities 4635

Tracker Requirements & Interface Control Documents

Title Mu2e-doc-# Title Mu2e-doc-#
Science Driven Requirements 4381 Tracker Front End Electronics Requirements 3879
Tracker Requirements 732 Tracker Interface Control Document 1562

Tracker Design & Specifications Documents

Title Mu2e-doc-# Title Mu2e-doc-#
Straw Tube Procurement Specifications 8091 Straw Advanced Acquisition Plan 7960

Tracker Construction Readiness Reviews & Oversight Committee

Title Mu2e-doc-# Title Mu2e-doc-#
Replies to Recommendations from Construction Readiness Reviews 11663 Replies to Recommendations from Design Reviews 6258
Report from the Straw CRR 8092 Replies to Recommendations from Straw CRR 9471
Panel CRR Report 20592 Response to Panel Recommendations 20595
Panel Follow-up CRR Report 30040 Response to Recommendations from Panel Follow-up CRR 30542
Tracker Construction Readiness Review Website Website Tracker Oversight Committee Website
Schedule of Upcoming Construction Readiness Reviews List      

Tracker Safety & Quality Documents

Title Mu2e-doc-# Title Mu2e-doc-#
Mu2e Subsystem Quality Planning Document
6005 Tracker QA Database
6865
Quality Assurance - Tracker Electronics
7196 ESH&Q Review - Tracker Straw Assembly (UofM)
7950

For assistance in obtaining any documentation, references, etc., please contact . For document content questions, please contact the appropriate L2 manager (see Project Contact List).