Additional questions/comments:

 

Previous version can be found here. Updates in this version are shown in red, while unchanged responses are in blue. Backup documents are:

3879, 2310, 2535, 5777, 5331, 1808, 5256, 5246, 2633, 1343.6099

 

1.      Looking at the layout the straws do not overlap around the straw center. Can you provide plots from MC of the straw resolution versus distance including electronics?  (even if it is not exactly within the scope to review the performance requirements).
Plots from simulation for time division resolution can be found here. “V” is the coordinate along the wire. Similarly, drift time resolution from simulation is presented here. “Reco drift radius” is drift distance based on fitting the track over all hits, while “true drift radius” is drift distance directly from the simulation.

 

The simulations assume the electron signal is 10x the rms noise and the threshold set to 5x the rms noise.

a.       How do you verify these with the prototypes?
An 8-straw prototype being tested at LBNL includes a pixel detector.  Although not it’s primary function, this can also measure resolution. Initial results are presented in document 6168. The noise level for these tests was higher than expected and, not surprisingly, neither resolution (>200μm) nor efficiency (<50%) meet our requirements. The test will be repeated in the near future.

b.      Does the MC include the discriminator threshold level achieved with the prototype electronics?
Yes, but using thresholds achieved with bench tests. A more complete understanding of noise and thresholds is in progress.

c.       What is the gas gain and how has it been measured?
We expect to run ≲5·104. Gain is measured using total current with Fe55 and using the known primary ions from Fe55.

d.      Has the noise level been measured?
Yes. With bench tests – straws attached, but no other electronics present -- it agrees well with Spice simulation

e.       Can you meet the required resolution and efficiency specs with present S/N?
Yes: With gas gain of 5·104 and assuming S/N is what we expect from SPICE and measure in bench tests. We note we have not achieved this in a realistic setup and there is a risk we will need to increase the gas gain.

2.      Can you describe in more detail the cooling system? Have you done any simulations or tests with realistic geometry of heat loads (boards) and cooling interfaces? What is the temperature of the coolant and electronics (overall temperature gradient)?
Documents 2068 and 2013 provide considerable detail. Both simulation and bench tests have been done. See documents 4087 and 4085. Revisions since that time in panel design improve heat transfer (more aluminum) and lower power. These have been analyzed but presented in a less self-contained manner; see for example document 5208. The coolant will run ~25C and gradient is ~3C.

3.      Can you provide details (drawings) of the vacuum sealing of the panels and how the assembly and leak testing is carried out?
Hopefully we can go over this interactively with 3D models.

4.      What are the characteristics of the fuses and have they been tested?
The fuse consists of a small torsion spring soldered under tension to conduct HV. One side uses a low-temperature solder which is melted using a heating resistor. It was tested extensively this summer and the document for it will be uploaded soon.

5.      How have you reached the conclusion that the inside and outside of the straw do not have to be connected?
No. Given the ambiguity of the conclusion, and the difficulty of assuring there is no connection, we have (tentatively) decided to make the connection.

6.      Can you explain in some more detail with a drawing or diagram the connections of the services (HV, LV and gas) i.e., patch panels, position of connections and modularity?
We do not yet details of the layout. Planned modularity is:
- One pair of LV lines per panel, 48V, with stepdown at the panel
- One pair gas lines per plane, with “fanout” outside the DS.
- We have left space for 960 HV lines inside the DS, fanned out from 192 HV channels outside the DS. We have not yet settled whether we need so many or how to distribute them if we do.

7.      Can you describe the plan in case of failure/problem with HV, LV, leaking straw and readout problem?
The general short-term solution to any problem is to disable the smallest possible segment of the detector and continue running. Longer term the plane is removed and the panel replaced. The defective panel can then be repaired while data taking continues. “Smallest possible segment” is a panel for LV or readout; a single straw for (most) HV problems; a plane for gas problems.

8.      It would be good to produce a detailed circuit diagram with characteristics and values of the components.
These exist, but perhaps should be coalesced into a single document.

9.      In the aging test you have seen no change in gain up to 1C/cm. Have you seen any effects on the straws?
Straws were cut open to examine for discoloration or other visible damage. End to end resistance measurements were also done. There was no indication of radiation-induced damage.

10.  Can you outline the development plan towards the final electronics?

a.       What additional prototypes are planned?
The push right now is for 2-channel preamps. Work on analog and digital motherboards is in progress. Prototypes for mother boards will be produced by early CY16.

b.      What questions remain unanswered and when do they think they will know enough to go into production?
Two vs single channel preamps, and details of the preamp to straw connections, are major concerns. I expect them to be settled by the end of this year. A lower probability, but higher impact, issue is radiation damage. Tests will be performed at LBNL this fall (October).

c.       What risks do they see in the near future?
The biggest risk is radiation sensitivity. In the unlikely event it is a problem, it could require major changes.

d.      How much schedule and cash contingency do they have in the baseline plan?
We cannot begin with production electronics till CY17, which is adequate time. We have ~40% contingency. Sadly not cash, we have to beg and plead to get it released.

Comments:

1.      It is important to do the radiation test of the electronics.

2.      It is recommended to repeat the discharge tests with the smaller blocking cap.

 

Comments:

 

This section summarizes the comments and conclusions by the review committee after the first two video meetings:

 

1.    It is the review opinion that the project is in good shape in view of the present schedule.

2.    The review committee thinks it would be useful to establish a clear grounding and shielding plan that is based on their present design status.

3.    A simple drawing of how signal and HV currents flow might be instructive (and also help define the grounding and shielding plan).

Some information regarding HV is provided here. Low voltage is described in document 6099. The baseline plan uses exclusively fiber optic communication, so there is no grounding or current issues. We are looking at copper and determining how to create a ground break will be part of that study.

4.    Interaction at an early stage with the FNAL safety team in order to get the green light for the planned electrical scheme and choice of components may avoid surprises and problems in the future.

An electrical integration team, headed by Karen Byrum and Gary Drake (both of Argonne), is working to ensure the various systems have consistent grounding scheme. The design will then be reviewed for safety.

5.    The reviewers felt that the layout and choice of components should not be left entirely to the DAQ group - the reliability problems with commercial electro-optical converters (let alone radiation hardness issues) are not to be ignored. The possibility to move the sensitive parts/components outside the detector to a more accessible area with little cost, should be considered

We work closely with the DAQ group as part of the ROC and integration tests. We are also looking at non-optical communication to bypass problems with electro-optical converters.

6.    The idea of using the CERN rad hard I/O equipment, as a fall back is plausible, but expensive. However, this option also contains a reliability worry and it needs to be examined in more detail, if considered as a real option.

7.    Concerning the fuses, a document describing design and validation is required.

8.    It would be to useful to establish a plan including the different tests and validations foreseen before CD3b e.g., electronics tests, radiations tests and a full system test.

Electronics

·       Test 2‑channel preamps with cosmics using the test chamber at LBL. Nov ’15

·       Instrument (including digitizers) eight straws on panel v1.5. Test with cosmics and, if available, test beam. Dec 15

·       Finalize ROC and digitizer. Oct-Dec 15

·       Test revised ROC+Digitizer board. Jan 15

·       Neutron damage (total dose) tests. Coordinate with test of plastics used for construction (below).

·       Depending on outcome of above, explore vacuum rated coax as an alternative to fiber. (If electro‑optics looks ok this may be postponed till after CD3c).

We do not want to design a full-size Analog Mother Board (AMB) which is not compatible with v2.5. Depending on how fast v2.5 design is finalized, we may instrument all of panel v1.5 before CD3c.

Full plane test is post-CD3c.

Mechanical

The immediate push is to test design changes from v1.5 to v2.5. See document 6225.

 

9.    A link to the plots from the simulations (by Dave B) including momentum resolution should be provided. The space resolution close to the wire is usually not so good and there is a gap between the straws in the double layer of ~1.3mm.

Link to Plots

10. A lot of work has been done on testing and validation. A link to beam test set-up, noise measurements, gain measurements and results would be useful.

See documents 5777 for proton beam tests. See 6168 for LBL’s cosmic ray setup and preliminary results, and 6265 for updated results.