CD-3a Review of Mu2eJune 10, 2014 |
Review Documentation Home Page |
![]() |
The Mu2e Project participated in a DOE CD-1 Review in June 2012 and was awarded CD-1 approval in July 2012. This is a
CD-3a review to authorize purchase of production lengths of the superdconducting cables needed to fabricate the Mu2e
Production and Transport solenoids. The cable is a long lead item.
![]() |
Jump to: Bottom of page    Documents for This Review    Documents from Past Reviews
Time | Title | Speaker | Mu2e-doc-# |
09:00 | Executive Session | (Committee) | |
09:15 | Project Status and CD-3a Readiness | (R. Ray) | 4227 |
09:55 | Discussion | (All) | |
10:10 | Coffee Break | ||
10:30 | Conductor Design and Requirements | (M. Lamm) | 4220 |
11:10 | Discussion | (All) | |
11:30 | R&D Conductor Performance and Production Readiness | (V. Lombardo) | 4221 |
12:00 | Review Summary | (R. Ray) | 4228 |
12:10 | Discussion | (All) | |
12:30 | Working Lunch | (Committee) | |
13:30 | Q&A with Project Team | (Committee) | |
14:00 | Executive Session | (Committee) | |
15:30 | Closeout | (K. Fisher) | |
16:00 | Adjourn |
Title | Mu2e-doc-# | Title | Mu2e-doc-# |
Review charge | here | Review agenda | here |
Committee Membership | here | Project Contact List | 245 |
Conceptual Design Report (CDR) | 1169 | Summary of Recommendations concerning the solenoid superconductors | 4215 |
  Concerning the Conductor Procurements: |
|||
Conductor Specification Packages | 2488 | Solenoid Aquisition Oversight Committee Web Page | Here |
Advanced Acquisition Plan for Solenoid Condoctors | 2493 | Advanced Procurement Plan for DS Conductor | 2474 |
Advanced Procurement Plan for TS Conductor | 2475 | Advanced Procurement Plan for PS Conductor | 2476 |
Mu2e Procurement Management Plan | 2350 | Mu2e Vendor and Sub-Contractor Oversight Plan | 2490 |
  Concerning the Solenoid Designs: |
|||
PS Reference Design | 3647 | DS Reference Design | 3664 |
PS Drawings and Solid Model | 3732 | DS Drawings and Solid Model | 3733 |
PS Procurement Specifications | 3669 | DS Procurement Specifications | 3670 |
PS Requirements | 945 | DS Requirements | 946 |
TS Preliminary Design | 4214 | ||
TS Requirements | 947 | ||
Tolerance studies for the DS | 2870 | Affect of coil displacements on the magnetic center | 2403 |
Tolerance studies for the TS | 2156 |
Title | Mu2e-doc-# | Title | Mu2e-doc-# |
Feedback from DOE Briefing (February 2014) | 4154 | Responses to feedback from DOE Briefing (February 2014) | 4155 |
Feedback from DOE Briefing (September 2013) | 3456 | Responses to feedback from DOE Briefing (September 2013) | 3457 |
Final report from DOE Mini Review (April 2013) | 2938 | Responses to recommendations from DOE Mini Review (April 2013) | 2939 |
Final report from DOE Mini Review (November 2012) | 2577 | Responses to recommendations from DOE Mini Review (November 2012) | 2579 |
Final report from DOE CD-1 Review (June 2012) | 2357 | Responses to recommendations from DOE CD-1 Review | 2358 |
Final report from CD-1 Director's Review (April 2012) | 2209 | Responses to recommendations from CD-1 Director's Review | 2240 |
Final report from Independent Design Review (May 2011) | 1563 | Responses to recommendations from 2011 Independent Design Review | 2067 |
Closeout report from CD-0 review | 382 | CD-0 Mission Need Statement | 720 |
Jump to: Top of page    Documents for This Review    Agenda and Presentations