CRV Technical Oversight Committee

Documentation Home Page

The Mu2e Project completed its preliminary design phase and achieved its DOE CD-2/3b sign-off in March 2015. The project expects to obtain CD-3c, approval to construct the detector apparatus in early summer 2016. In preparation for this, the project has asked panels of experts, in the form of Technical Oversight Committees, to provide advice on the design, construction, and installation plans of the detector. Critical to the experiment is the Cosmic Ray Veto, which surrounds the Detector Solenoid (DS) and half of the Transport Solenoid (TS) and is used to reject background events from cosmic rays. In order to meet the Mu2e design SES of 3E-17, the CRV must achieve a veto efficiency of 99.99% while operating in an intense radiation environment of neutrons and gammas. While the Mu2e design includes a significant amount of shielding to reduce accidentals in the CRV, this environment presents challenges to the scintillator strip based CRV design, which must produce ample light output to allow a sufficiently high threshold to be set to suppress most of the backgrounds. The Cosmic Ray Veto system represents significant cost, schedule, and technical challenges to the project. To help mitigate these technical risks, the CRV Technical Oversight Committee (CRVTOC) was formed. This web page collects information useful to the committee.

For assistance in obtaining any documentation, references, etc., please contact . For document content questions, please contact the appropriate L2 manager (cf. Project Contact List).


Note: documents linked from this page are password protected.

Agenda 23 September, 2015 (Chicago time)
Meeting room at Fermilab: TBD

Time Title Speaker Mu2e-doc-#
1:00 CRV Design (C. Dukes) 6040
13:45 CRV Module Fabrication (C. Group) 6041
14:30 Coffee All  
14:45 CRV SiPMs (P. Rubinov) 6080
15:30 CRV Electronics (S. Hansen) 6043
16:15 Discussion All  
17:00 Adjourn    

Additional Documents

Title Mu2e-doc-# Title Mu2e-doc-#
 
Cosmic Ray Veto Design and Requirements
     
Mu2e Technical Design Report [CRV (Ch. 10)] 4299 Science Driven Requirements 4381
Mu2e Conceptual Design Report [CRV (Ch. 11)] 1169 CRV Requirements 944
Cosmic Ray Veto Parameters 862    
 
 
CRV Oversight Committee Documents
     
CRV Oversight Committee Charge 6049 CRV Oversight Committee Membership Here

Reports and Findings

Title Mu2e-doc-# Title Mu2e-doc-#
Agenda and Presentations from 3-June-2014 Here Minutes & Responses from 3-June-2014 4250
Agenda and Presentations from 23-Sept-2015 This Website Minutes & Responses from 23-Sept-2015 6575


Last modified: 04/07/2016 |